The City of Bend and the Oregon Department of Transportation recently released a fresh slate of renderings for the Hawthorne Crossing, a $32 million footbridge to span the highway and railroad tracks in the heart of Bend. Those include concepts for transformed pedestrian plazas around the bridge landings and a clearer picture of the bridge’s aesthetics, with its rusted-brown steel support beams crossing to resemble the Three Sisters mountains. ODOT published the images and other new design details in an online open house Nov. 20, and will host an in-person open house with the City on Dec. 3.

Along with updates about the bridge’s look and feel, the public also got a clearer picture of the completion date for what is perhaps Bend’s most highly anticipated transportation project. And it’s later than previously thought.
ODOT says construction will likely wrap up in the first half of 2030, pushing out the previous timeline by about a year and a half. The City of Bend’s website says construction is expected through fall of 2028.
Reached by phone Wednesday morning, Bend City Engineer Ryan Oster said ODOT is leading the project and the City’s website hadn’t been updated to reflect the new timeline. He cited “questions about the availability of the steel we need to build the bridge” as part of the reason for the delay.
“The steel market is not great right now,” he said.

ODOT couldn’t immediately confirm the reason for the delay. Spokesperson Kacey Davey said Wednesday project staff weren’t available.
The vast majority of funding for Bend’s Hawthorne bridge comes from federal and state sources, including $20 million in Biden-era federal infrastructure funding, $5.7 million in earmarks from Congress and $5 million in Oregon Lottery funds allocated by the Legislature, along with $1 million from a City taxpayer transportation bond voters approved in 2020.
The timeline delay is not the first hiccup the City and ODOT have run into while planning the Hawthorne bridge. The Bend City Council chose a cable-supported design in 2024 only to pivot nearly a year later, due to unexpected costs.
According to ODOT, the truss-style bridge the City landed on will have lower maintenance costs and be easier to construct. That’s because the steel trusses can be assembled on Hawthorne Avenue and lifted into place over the highway and the railroad tracks, cutting down on closure times, according to ODOT.
ODOT said it expects “short-term” closures and up to two full-weekend closures of U.S. Highway 97 during construction.

Starting construction will coincide with the permanent closure of access to the Bend Parkway at Hawthorne Avenue. The block between the Bend Parkway and Hill Street will also be closed to vehicles, while a one-way street with a pedestrian promenade will extend to Harriman Street. A similar transition is planned for the bridge’s east landing.
New details released Nov. 20 show the bridge will have an 18-foot-wide path.
According to ODOT’s timeline, final designs will be completed in summer 2027, and construction bids will go out that fall.
The Hawthorne bridge is the most expensive of Bend’s Midtown Crossings, a set of projects meant to make for easier travel — especially for cyclists and pedestrians — across U.S. Highway 97 and Burlington Northern Santa Fe Railway. The City sees the bridge, along with a $16 million rebuild around the Franklin Avenue underpass, as catalysts to spur a planned urban core east of the highway called the Bend Central District, where redevelopment has been slow to take off. The Franklin Avenue project is expected to finish construction in early June 2027, adding improved storm drains, new bike paths, landscaping and lighting.